Bridge landing and double-height entrance works at Thornhill

CONSTRUCTION JOURNEY

How Thornhill is being transformed

A work-in-progress construction record of Thornhill's whole-house personalisation, including the new two-storey entrance hall, bridge landing, bathrooms, dressing room, cooling and connected systems.

← Back to the main case study
THE BUILD SEQUENCE

A current project, still in progress

The whole house has been comprehensively replanned and the technology, lighting, cooling and interior fit-out are being integrated as the refurbishment develops.

01

Removing the bathroom over the entrance

The bathroom directly above the front door was completely stripped out, including the floor structure and associated joists, creating a dramatic two-storey entrance volume.

Double-height entrance structure opened up during the Thornhill refurbishment
02

Creating the bridge landing

Removing the former bathroom changed the first-floor circulation and created a bridge serving both sides of the landing.

Bridge landing and staircase taking shape at Thornhill
03

New family bathroom

A smaller bedroom has been converted into a much larger family bathroom as part of the upper-floor reconfiguration.

Bathroom first-fix and preparation during the Thornhill refurbishment
04

Principal suite

The new principal suite is entered through a relocated main entrance, from there you have access to a new dressing room,  an enlarged doorway leading out to a new roof terrace and double pocket doors into an en-suite, with a central wash area and separate toilet and shower zones behind glazed doors all finished in a mixed media of micro-cement and tiles. The principal bedroom features a floating bed, bespoke floating furniture, exposed brick walls and a feature media wall with built in tv and fire finished in micro-cement.

Interior first-fix and feature-wall works at Thornhill
05

Bespoke dressing room

Another bedroom has become the principal dressing room, with full-height storage, dressing table, central island with secure displays, secure wedding outfit displays and a brass rail & ladder. With built in lighting on a sensor, ceiling speakers and air-conditioning it has a mixture of modern and traditional styles.

Bespoke dressing-room joinery components being installed at Thornhill
06

Lighting, cooling and connected systems

Sensor and decorative lighting, built in LED lighting tracks, air conditioning, renewed electrics and a large communications cabinet distributing the music, TV, hard-wired internet, Wi-Fi, CCTV and alarm are being integrated through the house.

Kitchen services and ceiling details during the Thornhill fit-out
07

Current fit-out stage

Parquet and polyurethane flooring installation, open-plan kitchen progress, pressure testing and the wider interior fit-out are still under way. Thornhill is not being presented as a completed project.

Parquet flooring installation during the Thornhill interior fit-out
BEFORE · DURING · AFTER

A photographic progress record

This work-in-progress journey records Thornhill’s structural opening, double-height entrance and bridge landing, new bathrooms, kitchen and joinery fit-out, rear landscaping, lighting, cooling and connected-home systems as the refurbishment develops.

01

Entrance and structural works

The bathroom over the entrance was removed, the double-height volume opened up, and the new bridge landing and structural arrangement were formed.

Rear groundworks and excavation during the Thornhill refurbishmentStructural opening above the Thornhill entrance during demolitionNew structural beam within the Thornhill double-height entranceTemporary access within the double-height Thornhill entranceNew staircase and bridge structure within ThornhillRear excavation and groundworks with plant at Thornhill
02

Rear groundworks and external works

Rear excavation, external waterproofing, brickwork, garden steps and service details progressed alongside the internal refurbishment.

Rear excavation and external works during the Thornhill refurbishmentExternal waterproofing works during the Thornhill projectRear groundworks progressing across the Thornhill gardenRear landscaping and brickwork taking shape at ThornhillGarden steps and brickwork under construction at ThornhillCurrent external construction detail during the Thornhill refurbishment
03

Interior fit-out

Kitchen, flooring, decoration and bespoke dressing-room joinery show the project moving through its current interior fit-out.

Thornhill kitchen and living area during the fit-out stageDark cabinetry being installed in the Thornhill kitchenParquet flooring installation during the Thornhill interior fit-outFlooring preparation beside the Thornhill kitchenDecorating materials during the Thornhill interior finishing stageDressing-room cabinetry installation progressing at Thornhill
04

Work in progress

Thornhill remains an active project. Finished imagery and completion claims will only be added when the work is actually complete.

Thornhill exterior during the current construction stage
Current Thornhill project detailRear hard landscaping works nearing completion at ThornhillCurrent Thornhill project detailCurrent Thornhill interior fit-out detail
RETURN TO THE PROJECT

Back to the project page

The sequence records the current stages of the refurbishment only. Thornhill remains an active project and is not presented as completed work.